Project Background
The Angelin development, originally discovered by the El Diablo well in 1995, includes a new platform and four wells. It is located 60km off the south-east coast of Trinidad in a water depth of approximately 65m.
The new platform, BP's 15th installation offshore Trinidad and Tobago, has a production capacity of 600 million standard cubic feet a day (mmscfd). Gas flows from the platform to the existing Serrette hub via a new 21km pipeline.
Scope of supply
Mantis won the contract to supply the bulk pipe, fittings, flanges, bolting, and gaskets. We were asked to produce and supply materials quickly and in accordance with the BP specifications.
½″ – 16″ pipe, fittings, and flanges
Compact flanges delivered within five weeks
Stock materials tested in compliance with the BP specification
Outcome
Mantis Piping managed the entire scope from its US and UK offices and facilities. Local teams organized schedule management and witness inspections, ensuring a smooth outcome for the customer in terms of reduced administration and on-time delivery of products and documentation. In addition, we continued to support the customer in the commissioning phase of this project.
Compact flanges
Carbon steel fittings
Super duplex pipe